Monroe 2-Orleans BOCES Capital Project

November 2017 Capital Project Update

Rooftop air handling units were set over the classrooms currently under construction: cosmetology, welding and precision machining. Ductwork was installed to take the heating and ventilation from these roof top units to each corresponding room. 

Exposed ductwork and ceilings were painted in the welding lab and precision machining Labs. Ceiling grid and tile were installed in cosmetology and the new computer lab. New millwork and countertops were installed in the cosmetology dispensary rooms and prep areas. Bathroom tile is complete and vinyl wood floor is being installed in all cosmetology rooms. High density resinous flooring has begun in welding and epoxy painted floors will follow in precision machining.  All three cosmetology rooms received new shampoo and styling stations. 

Final touches and cleaning will begin to allow cosmetology to move to their new space the week of December 18. welding and precision machining will follow with their moves over the holiday break.

October 2017 Capital Project Update

The fall 2017 phase of the project continues to develop and is on track for the end of the year turn over. The three new cosmetology spaces are outfitted to supply water and drainage to the shampoo stations, electric to the styling stations and wallboard has been installed ready for finishing, primer and paint. The CTE welding space is roughed-in for electric and walls are being painted. The precision machining lab is following closely with similar work.

Structural steel reinforcement is nearly complete, this will support the new roof-top air handling units as well as the necessary exhaust fans for these labs. New LED site lighting has been installed at the WEMOCO bus loop concluding all the site lighting improvements for the capital project.

September 2017 Capital Project Update

Following school opening, finishing touches were completed throughout  the summer scope classrooms. Corridor floors were completed in the South  building and the contractor has begun work in the North Corridors. New  furniture was delivered to many of the classrooms to accommodate their  newly designed space.Demolition continued and is nearly complete  in the future three cosmetology spaces and the Engineering and Metal  Fabrication Academy welding classroom and the additional precision  machining lab.  Construction of the new spaces will include underground  plumbing improvements, air-handling unit replacement and electrical  upgrades.  New cosmetology shampoo stations will be provided and newly  donated machining equipment will be set in its new space. 

August 2017 Capital Project Update

The heavy workload during the month of August had contractors working  around the clock in preparation for the first day of school. The  following programs moved into their space: automotive technology, auto  body and collision repair technology, culinary arts, baking, food  services, health and exercise science, certified nurse assisting,  personal services, computer technology, advertising design/multimedia,  child and family development, outdoor powersports technology, heavy  equipment operation and maintenance and various Center for Workforce  Development (CWD) Programs. The new addition over at the  Educational Services Center became occupied with Special Education  Programs including pre-school, Work Activity Center (WAC) and Career  Planning Services.Demolition has begun for the fall work phase.  This includes new spaces for cosmetology and Engineering Metal  Fabrication Academy's welding classroom, along with an additionnal lab  for EMFA precision machining. 

July 2017 Capital Project Update

Demolition   has been completed for the classrooms to be turned over in  September.   Paint and ceilings are being installed through out. We are  just on the   edge of completing underground plumbing for various lab  spaces,   bathrooms and kitchens. Walk-in coolers and freezers have been  installed   in the culinary labs and exhaust hoods will begin this  week. Both   masonry and metal stud walls are near completion and we are  looking at   jumping over to areas we will be working in for fall. The  WEMOCO front   bus loop is complete and new sidewalks have been  installed. We will   return to finish up the front entrance walkway and  canopy next summer.   The ESC building wrapped up at the end of July and  staff has moved into   their space. A few odds and ends are left such  as final kitchen   hook-ups, professional development center technology  and a few   last-minute door replacements. A list was developed and  prioritized for   completion. Due to the intense workload at WEMOCO, we  will return to ESC   in September to address minor issues.  

June 2017 Capital Project Update

As the last of the buses pulled out for the summer, the contractors were  racing to get started. Demolition of the North building began in D  Wing, and a portion of B Wing. In the South building, the Audiology  program allowed contractors to get a jump start and finishes are nearly  complete with flooring to follow. The remaining classrooms in the South  building have been taking shape as well. The bus loop work in  the front of the North Building started the last week of June and more  unsuitable soils were revealed. Unsuitable soils are made up of organic  material that cannot be compacted when excavated to a finish grade. In  order to remedy  this problem, over-excavation took place in effort to  find native soil, some areas were as far as five feet below grade. Stone  and geo-textile fabric were placed to provide stable ground and proper  drainage.Final cleaning and finishes are taking place at ESC in  preparation for staff moving back to their permanent work spaces. The  traffic pattern will transition into the final stages when the ESC loop  opens to two way traffic. Heavy construction traffic will continue all  summer throughout the site. 

May 2017 Capital Project Update

As summer approaches we are gearing up for construction at WEMOCO.  Preliminary electrical and plumbing work began advancing our busy summer  schedule in both the North and South buildings. Material, equipment and  storage units have been arriving on a daily basis and can be seen  throughout the campus. Meanwhile we are approaching the final  stages of the administration spaces at ESC. Painting and finishes are  well on their way, roof top air handling units were set and the site  work is almost complete around the building. Lights, doors and ceilings  are progressing and all the exterior canopies have been erected awaiting  paint. The front loop transition is being developed into a two way  entrance with new curb front parking. 

April 2017 Capital Project Update

Since the April 3 staff move into the ESC addition, the front half of  the ESC building has under gone demolition. Ceiling, lights, walls and  flooring have been taken out and new walls have begun shaping the new  space. The roof has been cleaned and scraped to allow a new layer to be  installed and new roof-top air handling units will be set. Structural  footers have been poured at the front of the building for the main  entrance canopy.Finishing touches continued in the addition and  PD Center this month. Window treatments and the operable partitions were  installed. Exterior siding and site work will continue around the  addition and is expected to be completed within a few weeks.Work  at WEMOCO has progressed ahead of schedule. Over the spring break,  plumbers were able to hang copper lines for the new water supply coming  this summer. The electricians continue to work on preparing for the new  electrical service both inside and outside the building. 

March 2017 Capital Project Update

The ESC addition and professional development area wrapped up with almost all interior finishes. Flooring, final painting and fixtures were installed to prepare for the staff to temporarily relocate to this space. Exterior improvements to and around the addition will continue in the upcoming weeks. This includes siding, roofing and concrete sidewalks. The new temporary main entrance is now located in the rear of the building leading into the addition.

A similar sequence now begins with the front half of the building. Demolition has begun and the new build-out will commence shortly. The front entrance loop has been closed to traffic and doors 1, 2 and 3 are strictly for construction personnel at this moment. Roof work will be ongoing with repairs and new installation over the existing ESC building.

Site work has commenced as weather conditions are improving. Concrete sidewalks have been installed and will continue to wrap around the addition. The front entrance of ESC will get a new sidewalk and changes in the traffic pattern. Permanent fence will be installed in the ESC bus loop island and around the new parking lot that temporarily serves as the construction staging area.
Minor work is ongoing at WEMOCO to advance the intense summer schedule. New water lines are set in place ready for summer tie in.

February 2017 Capital Project Update

The ESC addition and Professional Development area are gearing up for  the temporary move on March 31. The addition received final coats of  paint and the casework is nearly complete with countertop installation.  The restrooms are awaiting plumbing fixtures; work on the floors, wall  tile and paint has been completed. The light fixtures have been  installed throughout and will be powered up as we approach the final  weeks. Window installation took place in the addition with exterior  doors and storefront entrances to follow.A crane was on site  twice this month, once to set the new transformer that brings power to  the ESC building and again to set a portion of the roof-top air handling  units to supply heat and air conditioning.The WEMOCO North  electrical room nears completion in preparation for high voltage gear.  The masonry walls are erect, roof work has begun and the concrete floor  will be poured in the coming days. The contractors also took advantage  of the February break and were able to layout water supply lines in two  of the WEMOCO North corridors advancing the summer schedule. 

January 2017 Capital Project Update

The ESC addition interior approaches completion with wall board, primer and paint nearly finished. Rough plumbing, electrical and mechanical scope nears the end so that fixtures and equipment can be installed.

The new Professional Development Center is taking shape with framing and wallboard complete; primer and paint to shortly follow. Aesthetic soffits and architectural curved walls are complete. The operable partition track is installed awaiting the partitions themselves in a few weeks. Duct work is near complete and rough electrical has been installed to support the state of the art multimedia system.

The former James Green room (conference room 7) has become construction space and quickly redesigned into the ESC Kitchen, Library and Professional Development offices. Demo on the large restrooms has begun.

Progress continues with construction of the new WEMOCO North electric room with footers and foundation complete.

December 2016 Capital Project Update

The Exceptional Children’s Learning Center is now weather tight and work is underway developing the interior. Wall framing and drywall is being installed and all the necessary mechanical, electrical and plumbing that are within these walls are complete. On the exterior, weather barriers have been applied to the walls using a roll-on technique similar to painting, over the top of rigid insulation board. The roofing has reached a stage where it provides adequate protection but needs final applications when weather conditions improve.

The professional development area is taking the shape of the designed space. Framing has begun in this area as well.  A great amount of structural steel work has been performed in this area as well, to reinforce the existing structure, so that operable partitions can be installed which will allow this space to be broken up into many different configurations.

November 2016 Capital Project Update

The Educational Services Center expansion can now be seen by anyone who enters the campus. The enclosure of the 15,000 square foot addition has been accomplished ahead of the winter weather. This space will be the new home for some of our Career & Technical Education, Pre-school and Special Education Programs. 

Construction will progress through the winter within the interior of the addition as well as our new Professional Development Space. These areas will be turned over in early spring 2017.

New and additional lighting have been installed throughout the parking lot, thereby, increasing safety after dark. The new water service and by-pass have been installed and are contained in the climate controlled box seen at the front entrance; the service will be put in use come spring. Remaining site work has been put on hold for the season and will begin again when adequate weather returns. 

We will continue to move ahead with construction activities in an attempt to advance the schedule.

View text-based website